I am facing payment budget check during the reversal of GRN. I was wondering why the system is checking the budget at the time of GRN it is nothing but putting back the actual consumed amount to the fund center

 

PR Created  1000 USD

 

PO raised     1000 USD

 

GRN Done     1000 USD

 

During the reversal of GRN, the availabilit time for the Fund center and Commitment item was only 500 USD, so the system is trhowing the error message as budget exceeded by USD 500

 

Please help to clarify on the abpve issue how to stop budget check during the reversal of GRN. We are using updating control as MM Goods Receipt in OFUP

 